there are three different mechanisms by which safety is inserted into the time estimates of almost every step of a project. "The first one is that the time estimates are based on a pessimistic experience, the end of the distribution curve. "The second is that the larger the number of management levels involved, the higher the total estimation, because each level adds its own safety factor. "And the third is that the estimators also protect their estimations from a global cut.