"Whenever a step in a project is a collection of several tasks, each done by a different person," Ruth explains, "the boss of this project asks each person for their own estimates, adds them up and then adds his own safety factor on top." "So, if one estimates his task to take five days," Fred continues, "and the following task of the same team is estimated to take another five days, the person in charge will give an estimation of thirteen days."