"Critical path is defined as the longest chain of dependent steps. Longest in time, of course." "I know," he impatiently says. Then more slowly, "The critical path is the path through the steps of building the building, making it functional and installing the machines in it. A total of one hundred fifty days." "The critical path," I remind the class, "determines the time it will take to finish the project. Any delay on the critical path will delay the completion of the project. That's why the project manager must focus on it."