probe missions, NASA has been applying both a soft “risk score” and more sophisticated Monte Carlo simulations to assess the risks of cost and schedule overruns and mission failures. The cost and schedule estimates from Monte Carlo simulations, on average, have less than half the error of the traditional accounting estimates.8