A burn down chart shows us what is left to do. In general, we expect the work remaining to go down over time as the team gets things done. Sometimes the work remaining changes suddenly, when scope is added or removed. These events appear as vertical lines on the burn down chart: a vertical line up when we add new work, or down when we remove some work from the plan.
Scrum: A Breathtakingly Brief and Agile Introduction