My main work this week has been making preparations to procure that new effluent treatment plant for my long standing commercial client.
The Environment Agency have been very helpful, and I now have a revised consent to discharge which fits the site, and have designed a plant to fit the revised consent.
All that remains now is to make sure that we have recommended suppliers for all of eth kit, and an installation contractor to put it all in place. I'm meeting suppliers on site next week to finalise that, and procurement should follow soon after.
Commissioning wont take place until the autumn though, due to long lead time on the main process units.
In the meantime I have enquiries to deal with from Malaysia, West and South Africa, Pakistan, (and less exotically), Ireland for various water process engineering services.
Published on July 06, 2018 02:53