Pinned to the left-hand wall opposite the construction schedule was another butcher-block-size sheet almost identical in form, except this one, O’Sullivan said, was called a “submittal schedule.” It was also a checklist, but it didn’t specify construction tasks; it specified communication tasks. For the way the project managers dealt with the unexpected and the uncertain was by making sure the experts spoke to one another—on X date regarding Y process. The experts could make their individual judgments, but they had to do so as part of a team that took one another’s concerns into account,