But if a project is falling behind, managers don’t want to wait until the next milestone arrives before they are alerted to the delay. They need to know and act as quickly as possible. Our data were so detailed that we could make a further set of subforecasts, so we invented “inchstones.” And we specified in detail beforehand who would be responsible for what. If MTR started falling behind under the new schedule, managers would know immediately, and they would know who must act, so no time would be wasted. With the Hong Kong government, we developed the inchstone approach into a general