We also found that early delays in procurement and political decisions correlated with black swan blowouts in the HS2 reference class. Interestingly, early delays are not seen as a big deal by most project leaders. They figure they have time to catch up, precisely because the delays happen early. That sounds reasonable. But it’s dead wrong. Early delays cause chain reactions throughout the delivery process. The later a delay comes, the less remaining work there is and the less the risk and impact of a chain reaction.