The first phase of a migration is de-risking it, and to do so as quickly and cheaply as possible. Write a design document and shop it with the teams that you believe will have the hardest time migrating. Iterate. Shop it with teams who have atypical patterns and edge cases. Iterate. Test it against the next six to twelve months of roadmap. Iterate. After you’ve evolved the design, the next step is to embed into the most challenging one or two teams, and work side by side with those teams to build, evolve, and migrate to the new system. Don’t start with the easiest migrations, which can lead to