Imagine starting on Monday morning with a four-day project and a one-day project on your agenda. If you deliver the bigger project on Thursday afternoon (4 days elapsed) and then the small one on Friday afternoon (5 days elapsed), the clients will have waited a total of 4 + 5 = 9 days. If you reverse the order, however, you can finish the small project on Monday and the big one on Friday, with the clients waiting a total of only 1 + 5 = 6 days. It’s a full workweek for you either way, but now you’ve saved your clients three days of their combined time. Scheduling theorists call this metric the ...more