alternatives facing the manager? 1. Assume that the task must be done on time. Assume that only the first part of the task was misestimated, so Fig. 2.6 tells the story accurately. Then 9 man-months of effort remain, and two months, so 4 1/2 men will be needed. Add 2 men to the 3 assigned. Figure 2.6.