By the end of the next Sprint, the teams’ velocity had gone up 50 percent. The new date for delivery was September 1. Still three months late even though they had accelerated from 20 points to 90 points per Sprint, over 400 percent! And still not good enough. So Brent and I gathered everyone together, from engineering to marketing to business analysts to compliance folks to management.