Ignacio Raguet

51%
Flag icon
in a “Risky” approach, you have a 10 percent chance of finishing according to your estimated schedule. Doubling your estimates gives you a 50 percent chance of on-time completion, and to be virtually certain of meeting your schedule, you have to quadruple your estimates.
The Art of Agile Development: Pragmatic Guide to Agile Software Development
Rate this book
Clear rating