Fred

63%
Flag icon
Velocity should be calculated using an all-or-nothing rule. If a story is finished, the team counts its full estimate when counting velocity. If a story is partially completed during an iteration, it is not counted at all when determining velocity.
Agile Estimating and Planning (Robert C. Martin Series)