If the project is date-driven, we can determine the number of iterations by looking at a calendar. Multiplying the number of iterations by the expected velocity will tell us how many story points or ideal days will fit in the release. We can count off that many points or ideal days into the prioritized list of user stories and see how much functionality can be delivered in the desired time.