it is useful to include a buffer in the determination of the schedule. A buffer is a margin for error around an estimate. In cases where there is significant uncertainty or the cost of being wrong is significant, including a buffer is wise. The buffer helps protect the project against the impact of the uncertainty. In this way, buffering a project schedule becomes an appropriate risk management strategy.