For onshore renewables plants, most studies suggest that grid connection accounts for in the region of 10 to 15 per cent of total capital expenditure – a not insignificant proportion. But, in the case of offshore wind farms, of which HKZ is of course one example, the proportion, unsurprisingly, swells. Anywhere between 15 and 30 per cent of the capital cost can go to grid connection.